Most of the walls on the second level were completed when we came in the middle of the day on Monday, with basically just the north east bedroom and effectively the entire second level ceiling left to complete the main framing on the second level.

View of the house from the road. Most of the second level walls are up with the second level ceiling to go.
View of the house from the tree at the North east corner. The northeast bedroom on the second level is the one room with walls remaining to go up. At the same time, you can see the longer boards stacking up on the side of the garage that will be used to help build the ceiling.

View of the house from the Northwest corner. There was still some discussion on exactly how the recessed entry would appear so it wasn’t done yet.

View of the framing of the bumpout and the quasi-interior wall of the Master bedroom.

One of the workers stands on top of the corner of a closet and bedroom wall in preparation for working on the second floor ceiling. Don't think I would be comfortable standing like that, but it seemed like the most natural thing in the world for him.

I discuss ceiling plans in the Master bedroom with Juan. W.D. was a little startled to see me climbing up the ladder, but based on the brackets going in on the bumpout support, I was afraid that the ceiling was about to be built flat instead of as a tray ceiling. Turns out I was right about the intention for a flat ceiling, but wrong about the significance of the brackets. We’re now putting in the tray.

View of the trenches (to carry away sewage to the septic tank and drain field) in the basement from the West side of the basement (Den). W.D. (looking up the stairwell) also sneaks into the picture.

View of the trenches in the basement from the East side of the basement (Den). W.D. and Preethi discuss plumbing rough-in plans for the basement.