Tuesday, August 18, 2009

August 18, 2009: Last of the floor tile and cabinets arrive

I went out to the lot Tuesday evening (Preethi had been there most of the morning) and snapped a few pics.

The foyer tiles. We were going for a kind of carpet look.
The foyer tile area viewed from the dining room.

And viewed from the great room.

All of the cabinets and vanities were delivered for the entire house, which means the kitchen cabinets and all the bathrooms. In theory, they're all going to be installed tomorrow, but they're certainly taking up a lot of space now; this is just the set in the great room.

Here's the cabinets in the kitchen.

More cabinets.

In the meantime, more grading was done on the back yard.

Dan was still busy grading the backyard (drain field) when I was there.

The basement railing was also stained. That probably happened earlier, but I hadn't been down to the basement.

The hole where we'll dump the bodies. Or a foundational pier for the steps. Probably the latter. Probably.

Monday, August 17, 2009

August 17, 2009: Staining and drainfield

Over the weekend, we visited the lot and ran into Dan where we found out the drainfield wasn't actually quite done as the number of required drainage lines had doubled, so that now the builders and the survey engineer think the drain field is ridiculously overdesigned (large enough to accommadate a 8 bedroom house - it's 4 bedrooms).

However, by Monday evening, the additional lines had been dug (cheaper than fighting the state for a few months while simultaneously delaying our certificate of occupancy) and some staining had begun on the railings.
View of the house at sunset.

Rebar that will be used to reinforce several concrete pourings in the near future.

The stained railing. Note neither the steps nor the floor have been stained yet. That won't occur until virtually everything is done.


Another view of the stain on the stair railings

Over hte weekend, Preethi and I picked out some tile and made a little pattern for the doorway. It'll be laid tomorrow and presumably grouted on Wednesday.

The larger (twice as big now) and graded (again) drainfield.

A better view of an inspection pipe on the septic tank.

The distribution box with ALOT more pipes. Originally, 4 holes had been left unfilled so that if there was ever a problem with the field, the same box could be hooked up to the reserve field. Now, every hole but one is taken.

Monday, July 6, 2009

July 6, 2009: Wonderboard and doors

When we visited on July 6th (Monday), most of the second floor doors were in and Wonderboard had been laid for the tile in the kitchen and foyer.

Looking from the great room into the kitchen. The grey stuff on the floor is the wonderboard.

Closeup of the Wonderboard in the kitchen.

Wonderboard in the entry (foyer).

View of doors in the bedroom on the east side of the second level. That's a closet on the left, entrance in the back, and an entrance to the second floor bathroom next to the entry door.

View of the mini-hallway in the master bedroom. Those are closets on either side and the doors to the master bathroom in the back.

View of the upstairs hallway. The doors are all in. That's the laundry on the right and another bedroom in the back.

Updated view of the great room. The window and door trim is all in. Wood is down. Drywall is up.