Saturday, June 27, 2009

June 26,27, 2009: Cornice work and drywall

After some more travel I got out to the house on the 26th and 27th. Since mostly cleaning occured on the 27th, I've grouped together pictures from both days.

While I traveled, the cornices were mostly added with just the gutters to add. In the terminology, I'm used to, the cornice is the part of the roof that extends out beyond the wall and is made of of several parts including the fascia (flat part on end of roof line) and the soffits (on the bottom part of the roof overhang). The best conceptual picture I could find of the fascia and soffits was at this Bob Villa site, but its terminology doesn't jive with what I'm used to. What he calls a cornice, I would call a frieze with the frieze, fascia, soffit all part of the cornice.

Picture of the house from the tree at the northeast corner of the lot. Most of the final grading has been done except for right up against the house.
Closeup of some of the cornice work. The front facing pieces are the fascia and the pieces on the bottom are the soffits.

Different view of the house with the cornice work done.

In preparation for the final grading, the added cinder blocks were sealed to limit water penetration. After that dries for a few days (read as next week) the back fill will be completed and graded.

A few trees got nicked with during the brick laying. The bark was trimmed (to limit insect infestation) and sealed. We had actually noticed this earlier and had trimmed the bark but hadn't sealed the trees as the folks we spoke with suggested that sealing actually retarded healing (sorta like a bandaid).

Trim getting ready.

The beadboard ceiling for the front porch.

Danny mostly finished off the basement steps. There will be a railing on the right, but this is about all we will do on the steps.

View of the house from the back. In addition to the cornice work, you can see where the Hardie plank has been added for the master bedroom bumpout and great room dormer. Those parts couldn't be brick (at least at a reasonable price) because there was no direct support for the weight (actually the weight only matters while the mortar is setting). An interesting note for me is I was spelling Hardie plank as "Hardy plank" for years until a few weeks ago when I saw it spelled out for the first time. Basically, it's concrete fiberboard and is "hardier" in all the ways that matter as compared to vinyl and also looks better (the last part is my opinion). However, it's actually named for its inventor - James Hardie.

Close up of the master bedroom bumpout.

In the not so distant future, there will be a concrete pad underneath the side (rear, really) door entry to the garage. To support the pad, there will be a couple concrete piers which has been prepped in the square holes visible in the picture above.

The drywall was finishing up on Thursday. I just thought it was cool to see someone working on stilts.

If you looked closely at the previous picture you would see that the drywall around the arch appears rounded. That's because we're using bullnose archway beads around the arch. While we've seen it in a few houses in Lynchburg, apparently the pieces needed for it (seen above) were not available in Lynchburg so they had to be brought in.

The first interior door was hung - between the garage and the rest of the house. The kitchen (and most of the rest of the main level) is to the left as you enter. That's Kate in the background in the bathroom and Preethi's head is poking out.

Virtually all of the ducts are now connnected. (This is the same room where the earlier War of the Worlds tripod attack occurred).

Thursday, June 11, 2009

June 11, 2009: More Bricks and Drywall

On Thursday, ALOT of drywall was hung and the bricks started to look close to being done.
View of the front of the house. They think they'll be done with the bricks on Saturday if there's no rain.

View of the house from the Northeast corner of the lot. The unbricked side gable will have a vent installed tomorrow morning and then bricks will continue on up.

View of the garage (east) side of the house - all done with the bricks.


Closer view of the northeast corner. Here, you can see where the jack arches over the windows are slid out a little bit (5/8") from the wall

With the scaffolding down, you can see the full soldier course over the top of the garage.

All of the drywall is now hung in the main level bedroom.

And in the main level bath.

And in the great room - including the fireplace.

Still looking at the greatroom, but now back towards the dining room. I really love this view simply because I've never lived in a house with a 55' long sight line (corner of great room 20x30 to corner of dining room 14x14). Hopefully when the decorative column is added, the effect won't be lost.

The fireplace.

View of the stairwell on the second level.

Viewing the second level near the stairwell and looking towards the master bedroom. The large hole is the whole house fan.
Preethi stands on the front slab. Tomorrow brick arches should start going up on the slab to frame the entrance.



Monday, June 8, 2009

June 8, 2009: More bricks and air handling

On Monday, I made it out to the lot late in the evening and quite a few more bricks had been added as well as some additional work on the inside (air handling and some work on the steps).

View of the fron of the house. This was around 8:30 PM, but the brick masons were still working. On the 6th (Saturday), bricks had just started to go around the front and now you can see that they're most of the way up the front.


Closeup of the dining room window.

A row (course) of "soldier" bricks was placed across the top of the garage. Typically, this is for appearance, and that was also a motivation here, but it wasn't part of the original plan. Instead, when the iron angle was placed to support the bricks over the garage, the masons noticed that the bricks were not going to line up well over the garage, so we told them to do a soldier course to clean up the lines. For consistency, this is now going to be reflected over the two windows on this side. Also since the iron angle was inset a little bit, we couldn't bump out the bricks 5/8" like we did for the front windows.

View from the tree in the Northeast corner. The last parts to get bricked will be the center side-facing gable and / or the front entry (not visible).

View from the backyaard. The back and this side were were already done last time I came out, but the yard was too muddy to walk out and take this shot.

The stairs to the basement were roughed in except for the steps.

The steps between the basement and the main level as viewed from the basement.

We also checked up on all the settings for the interior doors with Danny. The door salesman had done the initial markings, but we still had to change about 1/3 of them. Above shows the markings on our pantry door which indicates a 2' 4" door, swinging out, with the knob on the right side (for easier access from the kitchen which is to the right when facing the pantry).

The attic air handler was constructed (had been in pieces before) and connected to the ducts / vents for the second floor.

One of the ducts running in the attic. I'm assuming the duct is slightly elevated to allow the spray-in insulation to avoid direct conduction with the ceiling (below).

The attic air handler venting into the master bedroom.